Palo Alto / Mountain View Reclaimed Water Pipeline Project
Palo Alto and Mountain View are constructing a pipeline to carry recycled water from the Palo Alto Regional Water Quality Control Plant to customers along East Bayshore Parkway and in Mountain View’s North Bayshore area.
Direct any questions to the Palo Alto project manager, Jamie Allen, at 650-617-3130.
What you will find on this page:
Background Information
Construction Updates
Project Map
Construction Photographs
Frequently Asked Questions (FAQs)
Construction Update: [Date: 8/11/08]
The contractor’s night shift crew is completing installation of 30-inch-diameter ductile iron pipe by August 15, 2008 on East Bayshore Road in the vicinity of Matadero Creek . The night shift crew will return to day shift work upon completion of the 30-inch pipe installation.
During the upcoming months, three day shift crews will be pressure testing installed lines and installing final paving, final tie-in at the RWQCP, customer connections, air release valves, and blow-offs throughout the project area.
Other key work includes bridge crossings at Matadero Creek and Adobe Creek in Palo Alto and Permanente Creek in Mountain View.